ADU cost: what a backyard home costs, and which lines move the total
An ADU's cost is the sum of a few large lines: design, permits and fees, site work and utilities, the building itself, finishes, and a contingency. In UC Berkeley's 2021 survey of California ADU owners the median project cost $150,000, or $250 per square foot.
Your own total depends far more on your lot and the fee rules than on that average, and this site shows you each line and the rule behind it.

What does an ADU cost?
The honest answer is a range, not a number. The Terner Center's 2021 statewide survey found that 37 percent of the ADUs it asked about cost less than $100,000 and 71 percent cost less than $200,000. The spread comes from the type of unit and the lot: converting a garage that already has a slab, walls and a roof is a different project from building a new two-bedroom cottage at the back of a sloped lot with a long trench to the sewer.
That is why we do not publish a price of our own. ADU Cost explains the parts of the budget that are set by law, so you know what a city may and may not charge you, and the parts that depend on your lot, so you know which quotes to collect. Start with our guide to what an ADU costs, which takes the lines one at a time.
The cost guides
What an ADU costs
The lines that add up to the total, what the 2021 survey found, and why a per-square-foot number misleads on small units.
California ADU fees
Impact, school and utility fees, the 750 and 500 square foot thresholds, and the review deadlines a city must meet.
Prefab ADU cost
What the factory price covers, what still happens on your lot, and what to ask a seller to put in writing.
Modular vs manufactured
Factory-built, HUD-code and site-built units compared: approvals, foundations, titles and the cost lines that change.
Budget worksheet
Type in your quotes and your city's fees; it applies California's ADU fee rules and adds your contingency.
Paying for an ADU
Grants, loans, rent counted as income, contract payment limits, and the property tax on the new part.
Bay Area ADU costs
Pre-approved plans, city fee pages and the lot conditions that move site costs around the Bay.
Dallas–Fort Worth ADU costs
No statewide ADU law in Texas: what Dallas's ADU overlay and Fort Worth's code mean for a budget.
The lines of an ADU budget
- Design and engineering. Plans, structural calculations, a survey or a soils report where the city asks for one. Pre-approved plans can shrink this line.
- Permits and fees. The building permit and plan check, and any impact, school and utility connection fees, each capped by state law in California.
- Site work. Clearing, grading, drainage and the foundation; the line that varies most from lot to lot.
- Utilities. Trenching for water, sewer and power, and sometimes a larger electrical panel for the main house.
- The building. Framing to roof built on site, or a factory unit plus delivery, crane and setting.
- Finishes and contingency. Flooring, cabinets and appliances not in the base price, and a reserve for what the ground or the old house reveals.
Which costs are fixed by law?
In California, more of the budget is settled by statute than most owners expect. Under Government Code section 66311.5, as HCD's ADU Handbook (March 2026) describes it, a city may not charge impact fees on an ADU of 750 square feet or less, and above that size impact fees must be in proportion to the main home.
An ADU created inside existing space, and a junior ADU of 500 square feet or less, is not treated as a new residential use for water and sewer connection fees. School districts may charge only ADUs over 500 square feet. A city must decide whether an application is complete within 15 business days and approve or deny a complete one within 60 days when a home already stands on the lot.
Those rules make size a cost decision. An ADU drawn at 760 square feet can owe impact fees that the same plan at 750 would not. Our California ADU fees guide shows the thresholds with examples.
Is a prefab ADU cheaper?
Sometimes the building line is lower or more predictable, but the lines around it do not disappear. HCD's factory-built housing handbook says the state's design approval usually covers the factory-built structure only; the foundation, the utility connections and the installation are permitted and inspected by your city. What a factory-built unit does save is the city's plan check on the structure itself: a local department may not re-review HCD-approved plans or charge plan-check fees for them. The prefab ADU cost guide splits the factory price from everything else.
Bay Area and Dallas–Fort Worth
We cover two regions with very different rules. Every Bay Area city works inside California's ADU law, and many now offer pre-approved plans: San José's program lists plans from 476 to 991 square feet and can issue same-day permits on lots outside geologic, flood and wildfire hazard zones. In Dallas–Fort Worth there is no statewide ADU law: a 2025 Senate bill passed the Texas Senate but did not become law, so whether an ADU is allowed, and what it costs to permit, is decided by each city's code. Read Bay Area ADU costs or Dallas–Fort Worth ADU costs.
Who we are
ADU Cost is a free information and request service, part of the Contractor Near Me family. We are not a contractor and we do not build ADUs. We write down what the law and the published studies say, show our sources on every page, and, if you send us your plans or quotes, go through the lines with you by phone or email so you know what is missing before you sign anything. More on the about page.
Ask for a free ADU cost review
A few lines are enough: the kind of ADU you have in mind, roughly how big, and the city or ZIP. We call or email you back to go through the budget lines; sending this costs nothing.
ADU cost questions
Is the median ADU cost the same as what mine will cost?
No. A median is the middle of what other owners paid in 2021, across every ADU type and lot in the survey. Half paid more and half paid less. Your total comes from your own lines, which is why the budget worksheet starts empty and adds only your numbers.
Does ADU Cost charge anything to review my budget?
No. Sending the request form or calling costs nothing. We go through the lines you have, point out the ones that are missing and the fee rules that apply, and tell you which questions to put to your designer, builder or city.
Why do your guides show sources under every page?
Because ADU costs are full of numbers that travel without their source. Each figure we use comes from a state agency, a city page, a lender's published guide or a university study, and it is linked so you can read the original and check that it still applies.
Sources: UC Berkeley Terner Center, statewide ADU owner survey (2021); California HCD, ADU Handbook, March 2026; HCD, Factory-Built Housing Handbook; City of San José, Preapproved ADUs; Texas Legislature, SB 673 history.